How to factor right-of-way cost into a candidate alignment ranking

Most alignment rankings get built on construction cost alone, because construction cost is the number you can price first. Cut-fill volumes come off a DEM, pavement sections come off a typical section drawing, and a cost-per-mile figure drops out the other end. Right-of-way cost lags behind, because nobody wants to run appraisals on three or four corridors before one gets picked. So it gets penciled in late, usually as a flat allowance per mile, and that allowance is often wrong in exactly the direction that matters: it understates the corridor that looks cheapest on paper.
Why ROW cost gets left out of early screening
The honest reason is that real ROW cost needs things a design team doesn't have yet at the screening stage: a parcel fabric, ownership records, maybe a few appraisals. Nobody is going to commission a title search on four alignments to rank them. So teams either skip the line item, or they apply the same per-mile allowance across every candidate, which has the effect of hiding the one variable that most often flips a ranking after the field crews go out: how much of the corridor runs through platted lots, active frontage, or built structures versus how much runs through open ag land or right-of-way the agency already controls.
A flat allowance treats a mile through a subdivision the same as a mile through pasture. Those are not comparable acquisition problems. One is a handful of ag parcels with no structures to buy out. The other is a string of partial takes, severance damage claims, maybe a relocation or two. The construction-cost model already tells you which corridor is cheaper to build. Without some read on what's actually sitting inside each corridor footprint, you don't know which one is cheaper to acquire.
Building a parcel acquisition cost estimate before you have parcel data
A usable proxy comes from knowing, for each candidate corridor, how much built-up area it crosses, what kind of land cover sits in the right-of-way strip, and where the structure density spikes versus where it drops to open field. A built-up mask and a land-cover classification laid over each alignment give you that read, without an appraisal. It won't give you a dollar figure for acquisition, but it will rank the candidates by acquisition exposure in roughly the order a real parcel count would, which is what you need at the screening stage: a ranking, not a budget number.
Run it alongside slope. A corridor that threads the low-structure-density ground might also be the one that climbs a ridge and needs twice the earthwork. That's the real tradeoff design engineers are trying to see before survey: does the alignment that's cheap to build turn out to be the one that's expensive to acquire, and does the alignment that avoids the built-up corridor turn out to need more cut and fill to get there. A one-off GIS exercise answers this for one project. Stacking land cover, slope and built-up masks against every candidate alignment at project start is exactly the ranking problem Route Selection Map is built to answer, and it's worth a look if you're doing this corridor by corridor in a desktop GIS session.
Weighing ROW cost against construction cost, corridor by corridor
Once you have a built-up exposure read for each candidate, pair it with the construction-cost number you already trust. You're not trying to merge them into one blended score. Put them side by side and look at where they disagree. The corridors where cheap construction and low built-up exposure line up are easy calls. The corridors where they pull in opposite directions are the ones that deserve the survey budget and the extra scrutiny, because that's where the final cost is most sensitive to which line item drives the project.
That disagreement is also the useful output to hand up the chain. A ranking that shows "construction favors A, acquisition exposure favors B" is a better starting point for a go/no-go conversation than a single blended number that hides which factor is doing the work.
If you're screening candidates right now and want that built-up, land-cover and slope comparison without building it by hand for each alignment, a constraint-scored map of your candidate corridors is worth a look before you lock in field survey.